Compliance & Cash

Mistakes that book unlicensed generation as unpaid YEKDEM

The plant runs; the cash stops. Contract power, the load link and the 2× cap can write a month to unpaid YEKDEM. On 1 MW an illustrative 586 thousand TL — the file decides, not this page.

  • Generation & Solar
  • 13 minutes

In unlicensed generation, inverter kWh does not mean the investor is paid for those kWh. In some cases the regulation treats the energy as if the incumbent supplier produced it: the market operator and the incumbent pay nothing; the record goes to YEKDEM as an unpaid contribution. The plant keeps running. The invoice line stops. Our unlicensed-solar compliance guide splits subscriber-group and transfer issues. This article looks at operational recording mistakes and the cash shock.

150 thousand kWh

1 MW example

Assumed monthly output

586 thousand TL

Commercial

VAT included, illustrative

5.86 mn TL

10 MW scale

Same unit × 10

0 TL

Severe outcome

That period’s generation fee

Why 586 thousand TL is serious

The example is a 1 MW unlicensed plant producing 150,000 kWh in a month and that month’s output being booked as unpaid. A rough commercial (ticarethane) active-energy equivalent including VAT is about 586,000 TL. The same assumption at 10 MW is 1.5 million kWh and about 5.86 million TL. This is not an EMRA tariff decision. The unit, band, subscriber group and VAT rate change by month. The point is scale: a loan instalment, an EPC balance or cash flow can vanish in one billing period.

Scale — commercial VAT-included illustrative equivalent (tariffs change)
PlantMonthly output (assumption)Unpaid-record equivalent
1 MW150,000 kWh≈ 586,000 TL
5 MW750,000 kWh≈ 2.93 million TL
10 MW1,500,000 kWh≈ 5.86 million TL

1. The contract-power floor (LUY 28/5 and 28/6)

The sum of contract powers in the associated consumption connection agreements cannot fall below the floor the regulation sets for that plant. The floor changes with invitation-letter vintage (after or before 12 May 2019), whether the plant is Article 5/1(h) plus municipality / industry / irrigation, and whether installed capacity or the application contract power is smaller. In our contract-power glossary entry the unit is kW, not kWh. If the floor breaks, that period’s output can be booked to unpaid YEKDEM.

  • After 12 May 2019, 5/1(h) “other person”: the floor is usually installed capacity.
  • 5/1(h) + municipality / industry / irrigation: a 2× build right exists; the floor is often the application contract power and rises to installed capacity if load exceeds the plant.
  • Before 12 May 2019: the floor is usually min(installed capacity, application contract power).

2. When the consumption site changes (LUY 28/7)

Ending the link or moving it to another load without the network operator and incumbent supplier knowing can book that period as unpaid. Even with notice the new site must still carry the 28/5 or 28/6 floor. If a wind/solar application won on the 14/6-b consumption criterion, the new sites’ annual kWh cannot be below the application consumption. “The factory closed, we linked the warehouse” is not enough on its own.

3. No load, line dead at acceptance, theft

  • If associated load has no electricity that month except force majeure (28/9), output can be booked unpaid.
  • If associated sites were not consuming at acceptance (28/10), the same risk lasts until they start.
  • After theft at an associated point (28/8), a proportional share may be unpaid that month and the next six billing periods.

4. Subscriber group, 2× cap, single supplier, storage

If associated loads after 12 May 2019 are not in the same subscriber group (30/6), that period’s output may be unpaid — detail in our unlicensed-solar compliance guide. In Hourly Netting 2026 and our unlicensed solar sales guide the 2× cap (26/17) applies except to households: the excess can still be netted; surplus after netting is unpaid. If several eligible consumers do not take from one supplier (23/5, 30/5), netting may not close. Export from integrated storage (Add. Art. 3) is not paid; if the share cannot be split, all surplus may go unpaid.

Risk family — what is read in the file? (summary; not a ruling)
QuestionWhy it is readCash at risk
Invitation-letter date?28/5 or 28/6Period output
Which Article 5 limb?2× right, closed ç/d salesSurplus or whole period
Σ contract ≥ floor?28/5–28/7Period output
Same subscriber group?30/6Period output
Annual 2× cap?26/17 (except households)Surplus above the cap
Single supplier?23/5, 30/5Netting + sales
Acceptance / SUA signed?18/3, 19/4Test / delay kWh

Why advice and monitoring sit together

The regulation is public. Application lives in the plant file. Saying “this month goes unpaid” without reading the invitation letter, connection agreement, Article 5 limb, YEPDİS / LÜM row and billing period together is wrong. The opposite is also wrong: changing the load link, contract power or supplier without reading the text. That is why our industrial energy-management pages keep the portfolio on one screen; the decision is still taken with an expert.

Close

Unpaid YEKDEM is the “we generated but it could not be sold” record. In a month, a 1 MW plant can lose hundreds of thousands of lira; 10 MW can lose millions. The text sits on EMRA’s unlicensed-generation page. Your ruling sits in the invitation letter, acceptance and associated load. The right order: have the file read, watch the floor and the group, close changes with the network and the supplier on the same day. The statute and the regulation stay here; the plant’s dates are read separately.

Tags

unlicensed generationunpaid YEKDEMcontract powernetting5.1hinvitation lettermonitoring

See the platform live

Request a demo or check pricing and our team will plan a presentation tailored to you.